This EWS1 remedial scheme was presented to BCS by the Developer in 2023 following a recommendation from the Fire Assessor. Following initial intrusive investigation it was established that there were two wall build ups that we perceived to be Fire Risks and in need of remedial works.

The two wall types are listed below:

Wall Construction - Type A
Wall Construction - Type B

BCS Cladding

There was approximately 1800m2 combined of both materials and the remedial specification required the ply substrate replaced with Fire rated timber which involved the entire bracket system being removed and reinstated as well.

The zinc system was reinstated upon completion but the entire timber cladding was replaced by composite boarding.

The works on this scheme are on-going.